Fatal Collisions

Current projects in response to fatal collisions

The following measures are remedial measures being designed and implemented following fatal collisions;

Location Measure Status Expected Delivery
Davidsons Mains Crossing/Roundabout Upgrade Progressing Re-determination Order to enable construction. Winter 2023/24
Murrayburn Road at Hailesland Road Signalised Crossing Project deisgn now complete. Tender process will take place in early 2023.  April 2023
Portobello High Street Road Marking/ Lane Alterations

Short term measures are now complete.   

The medium term measures are currently undergoing design and modelling. Wider public engagement will take place in 2023. 

 

More information on this project can be found at the following links:

October 2021 Committee Report

January 2022 Business Bulletin

March 2022 Business Bulletin

Medium Term - Autumn 2023

 

 

 

 

 

Contact Us

Should you have any further queries on the projects above, please contact us at the following email.